Home » Library » The Project Manager #8, September 2005 - Scheduling Best Practices
Scheduling Best Practices
To Avoid Changes, Delays, and Claims

For over 30 years, Pinnell/Busch has helped our clients reduce claims, resolve disputes, and improve their scheduling and we have developed Best Practices based on our experience. This spring, we surveyed industry practitioners to determine their experiences and recommendations to avoid changes, delays, and claims. We presented the results at the Project Management Institute College of Scheduling Conference in May. The report, a six-page summary, and the raw data are available on our website, www.pinnellbusch.com/library/.

Contract Changes
Project owners and contractors both reported that construction changes averaged 10% of their annual volume of work. Building contractors reported 8%, heavy/highway contractors 10%, and subcontractors 12%. However, individual owners and contractors reported widely varying results:
• Nearly half of owners averaged 5% or less of annual volume.
• Nearly one-fifth reported 15% or more and some reported 50%.

Reason for Variation
The wide variation is due to more than a difference in type of projects and working conditions. It must be due to a difference in procedures and standards. In other words, some organizations do a better job of limiting change than others. More importantly, major improvements are possible through better practices.

Cause of Changes
Both contractors and owners reported scope change as the primary cause of changes. Design errors and differing site conditions were the next most frequent causes, followed by owner delays.

Reducing Changes
Owners have control, or at least influence in the case of design, over 85% of the reasons for change. With better practices, owners can significantly reduce the extent of changes and, therefore, of claims and delays.

We prepared a list of Best Practices to reduce claims, as summarized in the adjacent figure, based on the survey responses and our experience on projects.

Claims
The percentage of changes that become claims varies widely – from zero to 50%, with an average of 61⁄2%. The wide variance between individual organizations means that major improvements can be made. There is a strong correlation between a higher percent of changes and more of those changes becoming claims.

Best Practices to reduce claims include: (1) better people skills and attitude/trust, (2) prompt and fair negotiation and payment for changes, (3) fair contract administration, (4) timely notice of change, and (5) clear communication. We strongly recommend partnering as the best overall method to avoid claims and help settle those that do occur.

Most claims (85%) are settled in negotiation with the balance by mediation, arbitration, or litigation. Mediation, however, should always be used before arbitration or litigation to save time, cost and business relationships.

Project ReAlignment, formerly called Intervention Partnering, is a new means of saving troubled projects midway through construction. It ‘wipes the slate clean’ with one change order for all delays and claims to date. Project ReAlignment turns around a troubled project in 30 to 45 days using a small team of experts and in-house staff. The cost savings are enormous and, unlike mediation, based upon documented facts. The ‘bleeding’ is stopped and progress resumes in a positive environment.

Delays
Half of all projects are delayed, with over 10% by more than 3 months. The variation between organizations is extreme: one- quarter of building contractors finished 95% of their projects on time, while half were 1 month late on 30% of their projects and 3 months late on 10%. Owners had similar records: 30% of municipal owners’ projects finished on time, but 25% had frequent or severe delays.

The causes of delay mirror the causes of change: scope change, design error, and differing site conditions. Other causes were poor schedules, third party delays, and weather. Most delays are under the owner’s control. Best Practices to reduce delays include those for reducing changes plus: (1) training in critical path scheduling, (2) owners writing better scheduling specifications, (3) contractors preparing better schedules, and (4) owner representatives enforcing the scheduling specifications and tracking of progress more closely.

Scheduling
Scheduling performance by all parties (contractors, owners, and owner representatives) was abysmal.

Owners’ Scheduling Specifications and Enforcement Most owners (60%) were satisfied with their scheduling specifications, but only half required narrative reports which are essential to understanding schedule logic, tracking progress, and identifying pending delays. Only half required electronic schedules, which are needed for independent progress tracking and delay analysis, or contemporaneous time impact analyses to justify delays.

Contractors’ Scheduling Procedures and Results
Most contractors (75%) were satisfied with their scheduling procedures and results – including many of those with frequent and/or severe delays. Owners reported that only one-third of their contractors were good schedulers, one-third were fair, and one-third were poor.

Subcontractors also had a dim view of general contractors’ scheduling practices, which closely matched the owners' responses. Too few general contractors requested subcontractor input, prepared monthly updates, kept the subs informed, or prepared recovery schedules when delayed. Worst of all, most hid delays and caused trade stacking.

Owner Representatives Scheduling Skills & Practices
Contractors had a very different opinion than owners of owner representative practices. The most serious shortcoming was untimely and unreasonable responses to RFIs and change order proposals, which was also one of the major causes of claims. The survey showed a clear relationship between timely and fair responses and fewer claims.

Best Practices
Our recommended Best Practices include those mentioned above, plus: (1) partnering, (2) achievable schedules, (3) accurate recordkeeping, (4) increased staffing on troubled projects, (5) win/win negotiation and mediation to resolve disputes, (6) training owners and contractors in contract law and scheduling, and (7) more timely submittal of and response to requests for information, notices of change, and change order proposals.

For details, call Steve Pinnell or see the full report on our website: www.pinnellbusch.com/library/.